989 Commission Drive, Fayetteville, NC
PWC Hometown Utility
7 Weeks
Commercial Building Remodel
Commercial Construction Contractors completed an addition and enclosure project for the PWC Seven-Bay Vehicle Shed.
Scope of Work: Construction of a 46-foot-long by 17-foot-tall wall using 8-inch concrete masonry units (CMU), installation of one main entrance door to match the existing doors, and installation of two new overhead doors to match the adjacent existing doors, Electrical and HVAC
Result: The project was successfully completed within the required seven-week schedule while maintaining an appearance consistent with the existing facility.