Hay Street, Fayetteville, NC
Houston Astros / Fayetteville Woodpeckers
Project 1: 5-day mobilization | 3-week completion
Project 2: 2 weeks
When the Houston Astros needed an urgent solution, they called CCC. Within just 5 days, our team was on-site and ready to work. In under 3 weeks, we completed the job—Installing new netting, involving structural and concrete work—ensuring a safe, secure environment just in time for the Fayetteville Woodpeckers’ Opening Game.
From rapid response to reliable execution, CCC delivers under pressure.
Commercial Construction Contractors was called in for an emergency repair project at SEGRA Stadium that had to be completed before the opening of the season. Working under a tight deadline, our team completed the required repairs within two weeks.
Update-Emergency Repairs:
Scope of Work: Replacement of custom 31-foot steel poles, concrete cutting and removal, removal and reinstallation of handrails and benches, and associated site restoration. Pour all concrete back with new rebar and anchor bolts
Result: Emergency repairs were successfully completed within the required two-week timeframe and before the stadium’s opening season.